The City of Fond du Lac owns and operates several stormwater pumping stations. Donohue & Associates was hired to make improvements to these facilities. The main goals were to improve the reliability, redundancy, and compliance of the city’s stormwater pumping infrastructure.
McDermott Park/Harborview Stormwater Pump Station: Donohue designed the installation of a permanent 600-kilowatt standby generator. This allows the city to operate two of the three 200 hp pumps during power outages. The generator is installed outside the pump station in a weatherproof enclosure. It was designed to be connected to the pump station via an automatic transfer switch. During a utility power outage, the automatic transfer switch will automatically start the generator and switch the pump station over to generator power. After the utility power has returned, the automatic transfer switch will automatically switch the pump station back to utility power and shut down the generator. The project also included a cursory review of the existing electric utility transformer, CT cabinet, and motor control center (MCC) in preparation for MCC replacement. Replacement of the MCC included reduced voltage soft starters to decrease the generator capacity.
East Scott Street, West Scott Street, and Main/Harborview Pump Stations: This project replaced the aging pumps and electrical systems at these pump stations. This included placing the electrical systems in a separate room to comply with current safety codes. Project design improvements also included a review of existing hydraulics to determine flow and head requirements for replacement pumps.
Consolidation Study: Donohue also investigated consolidating stormwater pump stations within the city to achieve long-term efficiencies and energy savings.