Lift Station Upgrades: Stevens Point, Wisconsin

The City of Stevens Point operates and maintains 15 lift stations that consist of multiple types of pumping stations including pneumatic, submersible, grinder, and centrifugal. These stations range in age from 8 years of service to 78 years of service. The lift stations have been well-maintained over the years, but several were at the end of their useful life.

Donohue worked with Stevens Point to complete design of improvements to the five priority lift stations. Donohue, in conjunction with the City, selected the most representative station and developed a preliminary generic design. During this design process, pumping system selection, layouts, and conceptual cost estimates were developed. Key aspects of the design were identified and developed with the resultant design serving as a “starting point” for the other pump station designs.

The purpose of the evaluation that preceded the design phase was to establish a standard pump station design and, over time, reduce the station variability throughout the system.

The end result provided similar pump station designs for each of the five pump stations to simplify operations and maintenance needs. Multiple types of pumping systems were reviewed prior to selection. The project included several workshops with the City of Stevens Point and Donohue staff to collaborate the design.

Stevens Point, WI - Completed Lift Station
Stevens Point, WI Completed Lift Station