The City of Elkhart, Indiana, and Donohue received an American Council of Engineering Companies (ACEC) Indiana Engineering Excellence Honor Award for the WWTP Capacity Upgrade – Phase II project, recognizing innovative, cost-effective solutions that improved system performance while meeting regulatory requirements. The award was presented at the ACEC IN Awards Banquet.
Elkhart is a growing community in north-central Indiana that relies on a robust wastewater treatment system to protect the St. Joseph River and comply with combined sewer overflow (CSO) regulations. To support long-term system reliability and meet the requirements of its CSO Consent Decree and Long-Term Control Plan (LTCP), the City selected Donohue as its engineering consultant for the second phase of its wastewater treatment plant (WWTP) expansion.
Rather than expanding primary clarification capacity and routing significantly higher wet-weather flows through the entire treatment process, Donohue proposed a cost-saving alternative using cloth-media disc filters (CMDFs) to treat wet-weather flows in excess of 30 million gallons per day (mgd). With the plant’s average day flow near 10.5 mgd and concerns about hydraulically overloading the secondary treatment process, the CMDF approach offered operational advantages and approximately 28.5% cost savings compared to the original LTCP concept.
Donohue coordinated with CMDF manufacturers and the City to conduct 5-micron pilot testing to evaluate performance. In parallel, Donohue worked with the City and its legal consultants to prepare technical documentation, data analyses, and regulatory submittals for the Indiana Department of Environmental Management (IDEM), U.S. Environmental Protection Agency (EPA), and Department of Justice (DOJ). Through multiple rounds of agency coordination and technical review, the CMDF technology was approved as an equivalent treatment approach, with additional WWTP improvements incorporated to enhance overall system performance.
Following regulatory consent, the City authorized Donohue to prepare construction bid documents for the new wet-weather CMDF treatment facilities and targeted upgrades to existing plant systems, including primary clarifiers, primary sludge equipment, aeration processes, return activated sludge facilities, and other associated components. Donohue also updated the City’s Preliminary Engineering Report (PER) to reflect the revised project scope.
The project was delivered in accordance with the Indiana State Revolving Fund (SRF) Loan Program requirements, with Donohue providing comprehensive design and construction-phase services to support successful implementation of this critical infrastructure investment.





Left to Right: Jeremy Roschyk, PE; Katherine Merkle, PE, LEED AP; Jason Simnick; Maggie Marnocha; Tory Irwin, PE, MPA