Comprehensive Wastewater Treatment Facility Upgrade: La Crosse, Wisconsin

The City of La Crosse operates the Isle La Plume regional wastewater treatment facility (WWTF) serving an extended sewer service area within the La Crosse metropolitan area and the City of La Crescent, Minnesota. The facilities were designed to treat an average flow of 20 mgd through the activated sludge process.

In preparation for anticipated strict phosphorus permit limits, the City elected to proceed with facility upgrades outlined in their 2040 Wastewater Facility Plan prepared by Donohue. In addition to improved biological phosphorus removal, the upgrades enhance safety, reliability, energy efficiency, solids processing, and solids reuse capacity. Donohue designed the recommended improvements to the treatment facility which included, among others:

  • Digester heating system including new boilers, heating loop, heat exchangers, hot water pumps, piping, valves, and instrumentation
  • Mixing upgrades to all four anaerobic digesters
  • Biogas piping, condensate removal, and waste gas burner
  • Biogas storage, treatment, and compression system
  • Heat and power cogeneration engine
  • Electrical utility upgrade
  • Upgrade to building hydronic heating systems
  • NFPA 820 compliance upgrades
  • Fine screen addition
  • Upgrades to the primary solids pumping system
  • Aeration basin conversion from A2O to MUCT system for enhanced bio-P removal
  • High efficiency turbo blowers
  • Rotating disc filters for phosphorus removal
  • Solids thickening Orege system
  • Belt filter press
  • Belt dryer with boiler and heat exchanger system, dust control system, odorous air control system, solids storage silo and load-out, and storage silo nitrogen purge system