Coldwater Creek WWTF Final Clarifier Replacement: Metropolitan St. Louis Sewer District, Missouri

The Coldwater Creek Wastewater Treatment Facility has an average daily capacity of 40 mgd and a peak flow capacity of 75 mgd. Donohue provided services to replace four existing square final clarifiers with one new circular secondary clarifier.

Clarifier Replacement

The surface overflow area of the new circular clarifier (130-foot diameter) is about one-half the size of the four existing clarifiers (each 80 feet by 80 feet). To determine the appropriate size of the new clarifier, a detailed analysis of five years of past operating data was conducted, which included the following: peak clarifier influent flow rate, surface overflow rate, solids loading rate, mixed liquor settleability, and clarifier performance. The improvements included the collector mechanism, center column, weirs, and associated controls.

Mixed Liquor Conveyance Capacity Improvements

A hydraulic model of the existing mixed liquor conveyance facilities was developed and used to test various modification scenarios to increase the hydraulic capacity into the final clarifiers. The recommended improvements included a combination of adding a small amount of new channel and the replacement of the influent magnetic flow meters with larger diameter meters. These modifications eliminated choke points found in the existing three circular final clarifiers, and the recommended plan also increased the height of the aeration basin weirs.

During the hydraulic model analysis, it was determined that the work associated with increasing the mixed liquor conveyance capacity would need to take place prior to removing the four square clarifiers from service in order to maintain adequate flow through the existing three circular final clarifiers.

Detailed Construction Sequencing

Because the new, circular clarifier was built in the same footprint as the four existing square clarifiers and mixed liquor channel modifications and meter replacements were necessary, the construction sequencing was quite complex and required greater attention during construction schedule planning. Furthermore, the project required existing facilities be taken out of service for extended periods of time but focused on minimizing downtime during construction. Overall, the construction schedule was a highly coordinated effort and milestone dates were included in the construction contract documents.

During the hydraulic model analysis, it was determined that the work associated with increasing the mixed liquor conveyance capacity would need to take place prior to removing the four square clarifiers from service in order to maintain adequate flow through the existing three circular final clarifiers.